Budget for Phase Four: 2007 – 2008

The Earth Corps for Global Service requires initial funding for the following expenditures, for the fiscal year August, 2007 through July, 2008:

Budget for Phase Four
Personnel to Implement Phase Four Tasks $161,000
Design Intensive conference: travel and hosting $ 25,000
Marketing development and consulting services $ 12,000
Technical consulting, legal, and accounting services $ 15,000
Travel to meet with potential coalition partners and prospective funders $   4,000
Printing and mailing $   1,000
Phone, FAX, office, and miscellaneous $   2,000
Total = $220,000

The activities made possible by these expenditures shall be overseen by the Board of Trustees of the Utne Institute, of which the Earth Corps for Global Service (ECGS) is a project amongst other related initiatives, for which it assumes full legal, fiscal, and operational responsibility. Said Board shall also assure the responsible expenditure of all funds and the issuance of a full annual report, to all contributors, as to such expenditures, along with a detailed accounting of progress towards the goals listed in the Phase Four section of the ECGS Timeline.

 